Limits on gas (TU on gas). Technical conditions for gas supply

Gasification of a site or a country house begins with the approval of gasification.

Technical specifications (TU) for gas is a document on the technical capabilities of gas supply through the main pipeline, it usually contains the following data:

the address and purpose of the facility, the possible volume of natural gas supply, the source of gas supply, the necessary measures “that should be taken to supply natural gas to the facility (for example, to reconstruct a gas distribution system, lay a supply gas pipeline, etc.)”, an indication of regulatory documents, validity period of gasification technical specifications.

Getting them is the starting point. Simply put, TU for gas supply is your request that Mosoblgaz allow gas supply to the site. You know very well that our government agencies are much forbidden to ban, and when you need to give permission, then a cold comes to their hearts and makes their way.

one for gas

In theory, everything is simpler than simple: I collected documents (I visited BTI, EIRTs, Moskomarchitektura, etc.), handed them over to the local Mosoblgaz branch (addresses of regional divisions can be found on their official websites), after 14 days I received the technical specifications for gas connections, referred the conditions to design organization.

In fact, everything is more prosaic and vital. You sit in line, and suddenly you find out that the application is only in print form accepted.

You quickly rewrite it, trying to recall what you were taught in the drawing class at school.

Now the application is in order and the technical specifications for gas and gasification will soon be on hand. But it turns out that the documents need to be submitted in the file folder as a brochure!

And finally (or even worse - the other day) it turns out that the package of documents is not complete. You brought only your passport data and BTI data sheet. And they also demanded a contract of sale, a certificate of state registration of ownership, information about the amount of gas you need.

If the house is at the design or construction stage, then add to the existing documents you need a plan for the location of the gasification facility, a building permit, a copy of the passport of the future facility.

Bureaucracy in one word.

The described situation is not an exaggeration. On the contrary, in practice, gas supply and the receipt of technical requirements require much longer time resources.

And if it was only in time. So after all, it is also strength and nerves.

In general, a standard set of “pleasant sensations” that every crossed threshold of any government institution receives.

And there are more difficult situations, where you can’t figure it out without specialists:

When compiling lists for gasification, a problem arises: in the beginning you need to incur large expenses. Some neighbors believe that you can wait until others hold the gas, and then inexpensively join the network.

In this case, the one who invests in the initial construction is at a disadvantage. This problem can be solved by registering a non-profit partnership for gasification, which will subsequently competently protect its shareholders and their interests.

We have gained considerable experience in these matters (registration of NPs, technical aspects of gasification).

How to be and what to do?

ELEZARGAZ company offers you to entrust the approval of technical specifications for gas supply to our employees who solve such issues DAILY. Work with any government agencies in the Moscow region.

You only need to visit our office and issue a power of attorney, which allows you to solve gasification issues on your behalf. All. Then you calmly go to work or rest, and at the same time know that the successful approval of technical specifications for gas is guaranteed by the specialists of our company.

We will collect all the documents for obtaining and coordinating the technical conditions for gas supply, which were mentioned above.

We stand for you all the lines.
  We have a fight with another official instead of you.
  But we will fulfill our obligations on time.

This is about coordination of technical conditions for gas "turnkey". The task is with you - the result is with us.

The cost of obtaining technical specifications for gas supply is from 25,500 rubles, but here options are possible, depending on specific factors.

A list of documents submitted by individuals to obtain technical conditions for connection to gas distribution networks of gas-using equipment of a residential building *

1. Application (of established form) - Appendix No. 2.

2. Copy of the applicant’s passport.

3. Title documents:

3.1. For existing buildings, any of the following documents:

- Certificate of state registration of property rights;
  - contract of sale, exchange, gift, etc.- (registered with the Federal Service for State Registration, Cadastre and Cartography);
  - lease agreement, with the consent of the owner.
  - the act of acceptance into operation;
- a technical passport (without statute of limitations) issued by an organization authorized to conduct a technical inventory (Bureau of Technical Inventory) as a document confirming the fact of creating a construction object;
  - permission to put the facility into operation.

3.2. For designed and under construction buildings - any of the following documents:

- Certificate of state registration of rights to the land plot with the appendix of the cadastral plan of the land plot / cadastral passport;
  - certificate of state registration of ownership, permanent (unlimited) use;
  - contract of sale, exchange, gift, etc .;
  - lease agreement, with the consent of the owner;
  - Decision of the Head of the municipality on the preliminary placement of the construction object, or on a design permit (in accordance with the requirements of TSN PPS-99 MO);
  - building permit issued by the head of the municipality.

4. Situational plan for the location of the gasification facility (A4 format).

5. * Permission from the Fuel and Energy Committee of the Moscow Region on the use of natural gas as fuel.

- to determine the hourly gas flow rate and the power of the installed gas equipment used to generate electrical energy, as well as to service pools, greenhouses, conservatories, etc. perform heat engineering calculation.

* The provision of the document referred to in paragraph 5 is not required when installing the following equipment:

1. If the gas-using equipment used by the population is household, flow and tank water heaters, household heating stoves, boilers installed in residential premises for the purpose of heating and hot water supply of these premises, with a total installed capacity of up to 0.5 Gcal / hour and maximum annual flow rate fuel up to 0.1 thousand tons (in conventional terms) per individual,

2. With built-in, attached, roof and freestanding boiler rooms with an installed capacity of up to 1.0 Gcal / hour (inclusive) and a maximum annual fuel consumption of up to 1.0 thousand tons (in conventional terms) per individual.

3. Technological equipment consuming less than 1 cubic meter. m of gas per hour.

(In accordance with the joint order of the Ministry of Economic Development and Trade, the Ministry of Energy of the Russian Federation, GAZPROM OJSC No. 333/358/101 dated 10/15/2002 "On approval of the procedure for issuing decisions on the establishment of fuels for enterprises and fuel-consuming installations and the list of gas-using installations and equipment for which it is not required to obtain special permits for the use of natural gas)

Gas specifications   - This is a document that allows owners of a boiler installation to connect it to a central gas supply system. Without this document, it is neither possible to develop project documentation for gas supply, nor to obtain an expert opinion, nor even proceed directly to the process of building a boiler room.

The technical specifications for gas indicate the amount of boiler fuel required for operation, the insertion point into the main pipeline, and also list all the measures necessary for the development, design and construction of the boiler house.

Obtaining gas specifications is not easy, especially in Moscow and the Moscow Region. TU for gas requires a whole package of various documents, and its execution in some cases may take about a year. In other regions of Russia, the process is usually somewhat simpler and takes less time.

To obtain technical specifications for gas, you need:

1. All available documents for the boiler room   - confirmation (certificate) of ownership of a land plot that is reserved for a boiler room, preliminary calculation of annual fuel consumption, statutory documents, etc.

2. Various approvals. In the package of approvals in Moscow   includes:

  • permission of the interdepartmental commission of the city of Moscow for gas, heat, electricity and water supply;
  • permission to use gas (to get it at the Department of Fuel and Energy Economy of Moscow);
  • a conclusion on the technical feasibility of supplying gas (to receive it at MOSGAZ);
  • technical conditions for gas supply (to receive - at "MOSGAZ);"
  • agreement on the use of gas from two organizations as fuel (to receive it from Mosregiongaz and Gazpromregiongaz);
  • coordination of volumes of gas supplied (to receive - to Gazprom).

Package approvals for Moscow region   slightly different:

  • coordination on the technical feasibility of gas supply (to receive it, go to Gazprom Transgaz Moscow);
  • coordination of volumes of gas supplied (to receive - to Gazprom);
  • preliminary technical conditions (to receive it at Mosoblgaz);
  • technical conditions for gas supply (to receive it at Mosoblgaz);
  • coordination on the use of gas as a fuel (to receive - from the supplier of natural gas with whom it is planned to cooperate);
  • coordination of the fuel and energy regime (to receive it - at the Ministry of Energy in the Moscow Region);

If it is planned to use more than 10,000 tons of standard fuel, it is also necessary to obtain the approval of the Ministry of Economic Development of Russia, and for residential and social facilities, permission from the Ministry of Housing and Public Utilities in the Moscow Region is required.

The minimum period for self-collection of all documents is six months, more often - as mentioned above - is delayed for more than a year. The help of qualified specialists in the preparation of a package of documents for obtaining technical specifications for gas will undoubtedly help to do this as competently as possible and as soon as possible.

If you plan to build a gas boiler house, turn to professionals for help - and you will receive all the necessary documents as quickly as possible.

Tekhnologiya heata LLC provides services for the design (confirmation) of the fuel regime.

The receipt (confirmation) of the fuel regime (the one for gas supply) begins after the registration of the volume "Calculation of heat and fuel needs".

The challenges of new construction

One of the most important stages, if necessary, the construction of new boiler houses or gas pipelines is to obtain various permits and approvals, and especially technical conditions for gasification.
In order to agree on the technical feasibility of using gas, to obtain technical specifications for gas supply, to obtain permission to build an autonomous energy source, to coordinate the act of choosing a gas pipeline route, it is necessary to spend from 2 months to a year. All these stages are often carried out by the Customer, since organizations that carry out the project do not undertake the operations to collect the initial data and pass the examinations.
As a result of this situation, the time required to commission facilities is being extended, money is being spent and the economic losses of customers are increasing.

Increase in gas limits (increase of technical specifications for gas)

If there is a need to increase the capacity of the existing boiler house, it becomes necessary to register an increase in gas limits. This process is similar in stages to obtaining limits from scratch. Specialists of Heat Technology LLC are ready to help in this procedure in Moscow and the Moscow Region as well as in other regions of the Russian Federation.

Registration of fuel modes (that for gas supply)

Our organization has a staff of qualified employees who can prepare a full set of documents but also assist in obtaining all approvals and conclusions in Moscow and the Moscow region.

The main technical conditions for the start of construction of a boiler house (mini-CHP) in Moscow are:
1. Conclusion of SUE “MOSGAZ” on the technical feasibility of supplying natural gas.
2. The decision of the Interdepartmental Commission on heat, electricity, gas and water supply facilities in Moscow.
3. Technical specifications for gas SUE "MOSGAZ"
4. Coordination of the technical feasibility of supplying natural gas from Gazprom Transgaz Moscow LLC
5. Approval by OAO Gazpromregiongaz of the use of natural gas as fuel.
6. Approval of LLC Mosregiongaz to use natural gas as a fuel.
7. Coordination of gas volumes of the Gas Distribution Directorate of GAZPROM OJSC
8. Permission to use natural gas from the Department of Fuel and Energy Economy of Moscow.


The main technical conditions for the start of the construction of a boiler room (mini-CHP) in the Moscow region are:
1. Permission from the Ministry of Housing and Communal Services of the Moscow Region (required if the boiler room (mini-CHP) belongs to the housing and communal services sector, social and sports orientation).
2. Conclusion of the technical feasibility of supplying natural gas from the State Unitary Enterprise MOSOBLGAZ.
3. Coordination of the technical feasibility of supplying natural gas from Gazprom Transgaz Moscow LLC
4. Approval of LLC Mosregiongaz to use natural gas as a fuel.
5. Coordination of gas volumes of the Gas Distribution Directorate of GAZPROM OJSC
6. Decision on the use of natural gas in the FUEL AND ENERGY COMMITTEE of the MOSCOW REGION
7. Coordination of the Ministry of Economic Development of Russia (provided that the volume of requested natural gas is more than 10 thousand tons of fuel equivalent)
8. Technical conditions for gasification of SUE MO "MOSOBLGAZ"

The time it takes to complete all stages of the fuel regime design can take from 2 to 9 months

In order to successfully connect to gas supply networks, all users must comply with certain conditions and provisions, which can be found by receiving a document entitled “Technical conditions for connection to gas supply networks”. They will be mandatory if the connection to gas supply takes place in a private or apartment building, industrial or communal enterprise. The document is issued by a special organization, after the subscriber submits the corresponding application.

Mandatory gas connection specifications

Obtaining technical conditions for gas connection for a private or apartment building, industrial or communal enterprise takes a lot of time. To do this, you must go through a series of procedures for collecting and submitting documents. The conditions prescribed in the technical specifications largely depend on how correctly the documentation is collected, the questionnaire is filled out.

To agree on a project, start construction and conclude a contract, technical specifications must follow all the rules and conditions specified in the document.

When drawing up a project of engineering communications, baseline data is taken into account. No linear object can be designed if there are no technical conditions. The data that is required in order to design a gas system is contained in the document on the technical conditions for connecting to gas supply networks.

What should be spelled out in the document:

  • Address of the object to be connected;
  • The place where the gas supply source is located;
  • The method of laying the main gas pipeline and materials for it;
  • Parameters possessed by the gas supply system and its tie-in point. It is important to evaluate the gas pressure, the allowed hourly gas extraction, gas pipeline diameter.
  • Description of the place where the insertion of a new pipe is possible.

The issuing and compilation of all documentation is handled by the resource supplying organization. Typically, residents of different cities of Russia, in Moscow and the Moscow region are engaged in this Gorgaz. There are other options for obtaining relevant documentation. You can clarify all the nuances by contacting the resource supply department.

Technical conditions for water supply connection

In the technical conditions, not only the main characteristics of the point at which the water supply is connected are indicated. The scope and conditions prescribed in the documentation depend on the area and area in which the technical work will be carried out on the connection. All the prescribed provisions usually take 1-3 sheets.



When compiling the documentation, the characteristics that the connecting parts should have are taken into account. Each user can learn how to negotiate and submit project documentation. It is better to choose a design organization on the advice of the water service.

What should be presented to individuals:

  • Passport, copy of passport;
  • Documents of the taxpayer;
  • The right to own a land plot;
  • Description of the situation on the site where land ownership is indicated on the map;
  • The consumption of water to be used.

A situational plan and a plan describing the location of the site can be obtained from the Administration. Before looking for a design organization and signing a contract, it is necessary to obtain technical conditions. The procedure for obtaining TU by legal entities is different - they must provide a larger number of documents.

Obtaining gas supply specifications

To make gasification, it is necessary to carry out design and installation work. Compliance with all gasification rules will make it possible to use gas, which can be the main source of heat supply, and also use it for economic and industrial purposes. The entire gasification process can be divided into three points: design, installation and commissioning.

The design phase is very important, since it must take into account all issues related to the immediate installation phase.

At the initial stage of design, you should learn all about the owner of the pipeline. The owner of the site may be GorGaz, RayGaz or the “cooperative”, which laid the gas pipeline on its own funds. The owner needs to know in order to turn to him for permission to connect to the gas pipeline.

What you need to know:

  • Before applying, you need to decide which heating equipment will be used, as well as in what place it will be placed.
  • When submitting an application with a request to obtain technical conditions, along with all documents, it is necessary to present a passport for heating equipment. As heating devices and devices that complement them, you can use the stove, boiler, meters, alarms, etc.
  • To speed up the process of obtaining permission may be turning to contractors for help.
  • When deciding to engage in designing independently, it is important to consider that you need to make an examination of the project, coordinate the project in special instances.

The necessary measurements must be carried out with the help of a design engineer. It is with its help that one can coordinate the arrangement of devices, the best and most suitable brand of equipment, draw up a scheme by which the gas pipeline will be laid in an apartment or house. If the project is being developed in GorGaz, the user must pay for the technical conditions and the project.

Calculation of gas requirements for technical specifications

In order to have technical conditions, it is necessary to provide a calculation of the gas demand. The main purpose of the calculation is to determine the annual consumption of natural gas using plants using gas (boilers). The calculation involves the content of information about power supply, ventilation, heating and those needs.

The maximum heat load can be calculated if there is information about the heat consumption of a certain type of equipment. The heat load on the hot water supply is based on data on taps and shower points. Boiler equipment is usually selected after calculating the heat load.



Nuances in the calculation:

  • It is important to correctly calculate the heat consumption on average per day and year. It is necessary to consider how much water will be consumed.
  • Calculation should be agreed upon in the structures that control this process.
  • Settlement can only be done if there is an SRO to carry out these types of work.

Obtaining a power of attorney for such a gas supply to a residential building is quite difficult, since the procedure requires painstaking preparation. A sample power of attorney can be downloaded on the Internet. The issuance of all necessary permits will take a lot of time. To simplify the procedure, you can use the services of specialized gas companies. How much are the services, you can find on the websites of companies.

What are the technical conditions for connecting to gas supply networks (video)

The power of attorney must necessarily indicate the validity period of the permit for use by the gas pipeline. After the deadline, you can get an extension. Before starting the design, it is important to determine the embedding of one or two gas pipes. The order of behavior of all procedures is important to know in advance. When calculating gas consumption, it is important to consider what the gas will be used for: cooking, heating, etc. You can not engage in a new project yourself. It is difficult to do this alone - it is better to use the help of a designer.